Eskom says that Koeberg Unit 1 will be commercially operational - i.e., supplying power to the national grid - on 3 November 2023, less than a week before Unit 2 is taken offline.
According to Eskom's generation division, Unit 1 of the Koeberg Nuclear Power Station reached a significant milestone on Friday 28 July 2023, when the mechanical work of the replacement of the steam generators was completed. This is the most significant part of the scope involving complex activities. It means that Eskom is now proceeding with the outage activities that could not be performed in parallel with the replacement of the steam generators. Immediately after the completion of the outage activities, the reactor will be reloaded with fuel, enabling the return to service of the unit. The commissioning, including the necessary tests of the new steam generators, will take place while the unit is synchronised to the grid.
Given all the outstanding activities, Koeberg Unit 1 is planned to be commercially available on 3 November 2023. Due to the postponement of the return of Unit 1, the outage of Unit 2 has been postponed to 7 November 2023 to ensure that there is no simultaneous shutdown of both Koeberg units. The utility says it can confirm that resources are ready to start with the first activities of Unit 2's outage.
The replacement of the steam generators was a first-of-its-kind complex nuclear project to be performed at Koeberg and is the last major plant component out of the three to be replaced on the unit as part of the long-term operation (LTO) project. The other two components, namely the replacement of the refuelling water storage tanks and the reactor vessel closure heads, have been replaced in previous years on both Units 1 and 2. The replacement of the steam generators is the last of the large components that Eskom deemed necessary to be replaced in support of its application to operate the Koeberg units for another 20 years.
The new steam generators are more efficient and will produce an additional 27 MW while enabling Koeberg to continue generating electricity for years.
The conservative design of the station, the investment that Eskom has made in continuously improving the safety standards, the rigorous maintenance as well as the testing programme over its operating lifespan, give merit to Eskom’s decision to apply for the licence to operate the plant for an additional 20 years. The Koeberg units have operated safely and reliably for almost 40 years. The amendment of the operating licence will enable Koeberg to continue providing safe, clean, and reliable power to the grid, and playing the essential role of stabilising supply in the Western Cape, which Unit 2 has safely continued to do with an excellent energy availability factor of 94,87%, while Unit 1 was offline.
Eskom would like to assure all stakeholders that the deferment of the Unit 1 outage does not negatively impact the licence application with the National Nuclear Regulator (NNR) to amend the Koeberg operating licence. Furthermore, as part of a continual improvement process, the power utility says it is analysing the causes of the delays at Unit 1 to ensure that they are not repeated during the upcoming steam generator replacement at Unit 2.